Is it necessary to prepare a corresponding plan for purging and pressure testing in the later stages of project construction?

2019-11-08View Original

Thread Content

Is it necessary to prepare a corresponding plan for purging and pressure testing in the later stages of project construction? Whether it is necessary to prepare a purging plan and a pressure testing plan, whether it should be prepared by the construction party or the project owner, and how such plans should be drafted?
Reply #22019-11-09
1. Who will write the plan? It depends on the type of project and the terms of the contract. Such as EPC: to be filled in by the general contractor.
Reply #32019-11-09
It definitely needs to be written; usually, the construction company is responsible for doing that – the person who operates the equipment is the one who writes it

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.