What is the reason for coking and blockage of the boiler slag discharge pipe after installing a return air fan in a 75t boiler?

2017-06-27View Original

Thread Content

What is the reason for coking and blockage of the boiler slag discharge pipe after installing a return air fan in a 75t boiler?
Reply #22017-08-04
It is possible that the increase in the amount of return material has led to an increased amount of slag discharged from the air distribution plate; as a result, the inner diameter of the slag discharge pipe is too small, and it can be replaced with one that is larger.
Reply #32017-09-13
The issue lies in the high carbon content of the fly ash in the fluidized bed boiler, which prevents it from reaching operating load. Engineer Liu 13002709449
Reply #42017-09-21
There is likely no direct cause; it may be that the air caps around the slag discharge holes are damaged, resulting in poor local fluidization and high temperatures.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.