Sequence of lining, hydrostatic test, and airtightness test

2022-06-10View Original

Thread Content

This post was last edited by zhangjuhua on 2022-6-16 at 17:02. Is the order 1 lining, 2 hydrostatic test, 3 airtightness test indeed that order? Line it first; what if the water pressure isn’t up to standard? Will the lining have been done for nothing? After consulting, it should be: 1 pressure test, 2 lining, 3 airtightness test
Reply #22022-06-10
What else? Qualified products can stand up to testing; it doesn’t matter if the order is disrupted: 412372706
Reply #32022-06-13
Shouldn’t normal be water pressure, airtightness, and lining?
Reply #42022-06-13
Hydraulic, lining, and airtightness testing of steel equipment.
Reply #52022-06-15
The strength of Uchimura is not very high, so generally hydraulic pressure is applied first, followed by air sealing in Uchimura

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.