Issues related to radiography for weld replacement in GB/T 150.4

2025-03-15View Original

Thread Content

Article 6.1.6 of GB/T150-2024 states: “...the joints thereof do not require weld replacement.” If it is thermoforming but trial plates are not allowed, in the case of weld replacement, does it require two X-ray examinations – one before the weld replacement and one after – or is just one examination sufficient, taken after the weld replacement?
Reply #22025-03-15
If replacement is needed, then aren’t the previous welds and the X-rays taken pointless?; The last X-ray was taken as preparation.
Reply #32025-03-15
According to the provisions of GB/T 150.4, under normal circumstances, an X-ray inspection should be carried out after weld replacement to verify the welding quality. If the specifications or project requirements dictate inspections also before weld replacement, two radiographs are taken; however, usually only one is taken after replacement to verify the integrity and quality of the weld. For specific operations, it is necessary to refer to the relevant engineering technical requirements or consult the quality inspection department. .
Reply #42025-03-15
Weld replacement – definitely take X-rays after the replacement.
Reply #52025-03-15
I mean, if no X-rays are taken, how can we know whether a replacement was done or not?
Reply #62025-03-17
X-rays must be taken after replacement; the welds before replacement are created for shaping purposes, and whether to take X-rays is decided based on the welding quality of the factory itself.
Reply #72025-03-17
https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5679483&highlight=%E7%84%8A%E7%BC%9D%E7%BD%AE%E6%8D%A2 This post might be useful
Reply #82025-03-17
An X-ray after the replacement is necessary; as for one before the replacement, it depends on your design and manufacturing requirements
Reply #92025-04-09
For certain materials, replacement is necessary, while ordinary materials do not require replacement

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.