Nitrogen blanketing of storage tank

2020-06-19View Original

Thread Content

This post was last edited by lanlanhaogao on 2020-6-19 at 17:20. There is a large storage tank that has been in use for over a decade, and it now needs to be modified to include a nitrogen seal. Breather valves and emergency pressure relief manholes need to be added to the tank top; what tests are required after welding? Is it necessary to obtain the consent and approval of the original design unit?
Reply #22020-06-21
The design must be carried out by a unit with relevant design qualifications; it is not necessary to use the original design team
Reply #32020-06-22
It must be designed by a qualified design firm or bear its signature
Reply #42020-06-22
First, the plan must obtain written approval from the original design unit or a design unit with corresponding capabilities; Secondly, go to the local supervision department to inform them and obtain their consent ; Third, the construction unit must possess the appropriate qualifications ; Fourth, supervision and inspection are required ; Fifth, it is necessary to obtain a new permit for use.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.