Question: The flue gas volume from the coke oven is 150,000 standard cubic meters per hour on a wet basis, with a humidity level of 10%. The requirements are that the temperature of the flue gas at the inlet of the waste heat recovery unit be 225°C, the temperature at the outlet be 150°C, and the saturated steam pressure be 0.64 MPa (gauge pressure). The inlet water is softened water at 20°C. Is it possible to achieve this? The temperature of saturated steam at 0.64 MPa (gauge pressure) is approximately 168°C. Can the flue gas be cooled to such a low temperature? Or, if it can be reduced to 150°C, its economic efficiency in terms of design is very poor.
Reply #22024-05-08
It is possible to do so, but a design that reduces the temperature to 150°C would indeed reduce economic efficiency. This is because the lower the flue gas temperature, the lower the efficiency of waste heat recovery; moreover, a larger heat exchange area and more complex equipment are required to ensure heat recovery, which in turn increases costs. .
Reply #32024-05-18
Based on the calculations, this is not feasible; the temperature difference at the narrow areas is essentially 0, so heat exchange can no longer take place. There are two solutions: 1 is to appropriately increase the exhaust temperature to 150. 2 is to reduce the steam pressure to below 0.4 MPa, so that the temperature at the narrow point can be maintained above ~15°C.
Reply #42024-05-23
It’s completely achievable; just draw two curves to see it – the inlet water temperature is 20°C, the steam temperature is 168°C, and the flue gas temperature ranges from 225°C to 150°C. It can be said that this level of recovery isn’t the best, but it’s sufficient. It mainly depends on what kind of recycling device you use. Evaluate the cost-effectiveness and the payback period for investment.
Reply #52024-05-23
I once developed a plan for waste heat recovery in a sponge titanium hot blast furnace; I forgot how to upload it
Reply #62024-05-23
Lowering the temperature to 150°C is no problem at all; it’s simple – just preheat the water supply, and the result will be excellent.
Reply #72024-06-12
I have worked on this project; you can refer to my website: http://www.fishsting.com/xxjh/soft/jlyrhs.html

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.