Does covering the steel utility pipe with soil after applying adhesive repair strips affect the results of electric spark testing?

2018-05-16View Original

Thread Content

As the title indicates, during the construction of steel underground pipes, it is necessary to repair the welds after performing a pressure test. Assuming that there are no damages in the areas of the pipe that are not weld joints, and that the soil layer has covered these areas during the pressure testing process, will the spark testing of the anti-corrosion coating be affected by the soil?
Reply #22018-05-21
The inspection of the anti-corrosion coating on buried pipelines should be carried out after the soil has been laid on top, otherwise it’s not possible to determine whether the anti-corrosion coating was damaged during the covering process

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.