HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Doubts about the design pressure of the torch water seal body and upstream and downstream equipment

2019-02-12View Original

Thread Content

In the design of the flare system in the Petrochemical Design Manual (Volume 4), page 647 is as shown in the attachment. I don’t understand why the design pressure of the downstream equipment is higher than the design pressure of the upstream equipment, and it is twice as high.
Reply #22019-02-13
The fact that you ask this question shows that there is not enough research on standards. Many things in the petrochemical design manual come from standards. Just look up the standards and you will know. SH3009-2013 Design Code for Petrochemical Combustible Gas Emission Systems, Article 8.2.11, is this provision. The explanation of the article clearly explains why the design pressure of the water seal should be 0.7MPa.
Reply #32019-02-13
Thank you, I have never contacted :handshake before

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.