HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

During the first start-up of the unit, when were the utility services introduced? Please, expert, help me understand this

2022-08-18View Original

Thread Content

Is the introduction of utility services done during purging? Isn’t it the case that for once-through water, fresh water, recycled water, and low-temperature water, they are all used after being purged with their own medium and then put into use directly after exhaust is released from the highest point of the equipment? Are the steam pipes also cleaned with steam, then drained through the drain lines, and the pipes are slightly opened to warm up before being put into use once the valves are fully open? I just want to ask the expert to help confirm it. . . :handshake
Reply #22022-08-18
Is it that after the constructor completes the work and makes the necessary corrections, the utility systems are put into use first, and only then is pressure testing, airtightness testing, water circulation testing, replacement, and commissioning carried out?
Reply #32022-08-18
Depending on the scale of the facility, it is generally necessary for the utility systems to be ready for operation or to start operating 3 to 6 months in advance. For example, only after fresh water, industrial water, desalinated water, wastewater, etc. are put into use can the boiler in the power center meet the requirements for operating a drying furnace ; Only after the 110 kV and 35 kV systems become capable of connecting to the external grid do facilities such as air separation units and air compressor stations become operational ; .....Only after water, electricity, gas (steam), air, nitrogen, etc. are available or operating normally can the facility be ready for tasks such as purging, system pressure testing, and individual testing of large-scale units.
Reply #42022-08-18
For details, please refer to: China Petroleum & Chemical Corporation’s “Regulations on Production Preparation and Commissioning for Construction Projects”, PetroChina Construction [2008] No. 268. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=563080
Reply #52022-08-21
Separate the two questions: 1. When is the demand for utility use? 2. What steps are required to put this utility medium into use, and how many days will it take to ensure a satisfactory supply? As per the reverse schedule above, that is the time when it will be put into use. For discussion reference

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.