Key points for pre-commissioning and linkage commissioning of chemical equipment Pipeline system pressure test 1. Pipeline system pressure test conditions a. The safety valve has been added with a blind plate, the blasting plate has been removed and a blind plate has been added b. The expansion joint has been restrained c. The spring support and hanger have been locked d. When water is used as the medium for the test, the bearing capacity of the relevant structure has been confirmed or calculated e. The pressure gauge has been calibrated 2. Pipeline system The pressure test should comply with the following regulations: a. Testing with air and process media must be approved by the design unit and production technology department; b. Before testing, confirm that the test system has been effectively isolated from irrelevant systems; c. When conducting hydraulic tests, use clean fresh water as the test medium. When austenitic stainless steel equipment or pipelines are connected to the system, the chloride ion content in the water shall not exceed 0.0025%. d. The test temperature must be higher than the brittle transition temperature of the material e. When testing is carried out in cold seasons, anti-freezing measures must be taken f. The pipeline pressure test should comply with* * Relevant standards and specifications require g. After the test, the water and air should be drained and reset with water flushing a. The pressure test has passed, the machinery, instruments, valves, etc. in the system have taken protective measures, the temporary pipelines have been installed, the flushing pump is running normally, and the filter can be installed at the inlet of the flushing pump before water flushing can be carried out. b. Flushing work should not be carried out in severe cold seasons. If it is carried out, antifreeze and anti-skid measures must be taken. c. When filling and draining water, the pipeline system should be connected to the atmosphere. d. Before the pipelines and machinery in the previous process are flushed, the flushing water must not enter the next process. e. The flushing water should be discharged into the designated place. f. After flushing, ensure that all drainage and exhaust pipes are unblocked. Instrument system commissioning 1. Conditions before instrument system commissioning a. The instrument air station has normal operating conditions, and the instrument air duct system has been purged to qualified standards. b. The air conditioner and uninterruptible power supply in the control room can be used normally. c. Transmitters, indicating and recording instruments, interlocking and alarm signaling switches, and regulating valves. And the single adjustment of panel-mounted and rack-mounted instruments has been completed. d. The relevant parameters of the automatic control system regulator have been preset. The feedforward control parameters, ratio values and various corrected ratio bias systems have been calculated and preset according to the relevant data. e. Various analog signal generating devices, test instruments, standard sample gases, communication tools, etc. have been prepared. f. All on-site instruments and the regulating valve are all in use. 2. The instrument system debugging should comply with the following regulations. a. The detection and automatic control system should be simulated and debugged before being jointly tested with the machinery, that is, inputting the signal at the transmitter, and checking all functions such as indication, control, and alarm on the operating console or secondary instrument. b. The interlocking and alarm system should be simulated before being jointly tested with the machinery. Debugging means inputting an analog signal at the signaling switch, checking its correct logic and action, and adjusting it until it is qualified. c. When jointly debugging and adjusting instruments with machinery, instrument, electrical, and process operators must cooperate closely with each other. d. For interlocking devices that are temporarily unavailable for initial commissioning or under load, with the consent of the construction (production) unit, they can be temporarily debugged. be removed, but the alarm device should be retained. e. Before chemical commissioning, the feedforward control, ratio control and control system containing the corrector should be re-set according to the load and actual material composition. Electrical system debugging 1. Pre-debugging conditions of the electrical system a. All installation work of the main substation and related debugging projects have been inspected and confirmed by the power supply department Confirm and complete the power receiving procedures b. Primary equipment such as isolating switches, load switches, high-voltage circuit breakers, switch cabinets, transformers, etc. have undergone handover tests and passed the test; c. Secondary equipment such as relay protection has passed the test; d. AC and DC operating power supplies have been debugged successfully; e. UPS and other emergency power supplies have been debugged successfully; f. Test records of grounding resistance are available; g. Electrical equipment is available. Test pass record h. Have interlocking protection test pass record. Electrical system debugging should comply with the following regulations. a. Power supply and distribution personnel must hold certificates to work and strictly implement the operating system. b. Before receiving power at the substation and power distribution site, simulation tests must be conducted on the relay protection device, automatic reclosing device, alarm and pre-phase system according to the system. c. On the programmable logic controller The protection device should simulate interlocking and alarm parameters one by one, and verify the correctness of its logical positive alarm value. e. The accident power supply system should be tested and confirmed.: a. The replacement flow chart has marked the venting point, analysis point and blind plate position. b. The sampling and analysis personnel are in place, and the analytical instruments and drugs are ready. c. The inert gas can meet the needs of the replacement work. 2. The system replacement conditions should comply with the following regulations.: a. The oxygen content in the inert gas shall not be higher than the safety standard. b. Confirm that the quantity, quality, and installation location of the blind plates are qualified. c. When replacing, pay attention to the dead corners in the system. If necessary, use repeated pressure increase and pressure relief methods to replace the gas. d. When the pipeline system is connected to a gas cabinet, the gas cabinet should be raised and lowered three times repeatedly to replace the gas in the annular water seal. e. The replacement work should be carried out consecutively in the order of first the main pipe and then the branch pipe. f. Analysts should pay attention to the wind direction and the height and direction of the vent pipe when sampling to prevent poisoning. g. The analysis data shall be subject to three consecutive passes and shall be signed and confirmed by the production, technical and safety personnel. h. After the replacement is completed, effective measures shall be taken to isolate the inert gas pipeline from the system.