Air conditioning energy consumption in clean areas

2025-06-04View Original

Thread Content

The clean area in the workshop covers 1,000 m2, with a cleanliness level of CLASS 10000. 1. Selection of the chiller for the air conditioning system in the clean area; 2. Methods for estimating the cooling capacity required by the air conditioning system
Reply #22025-06-05
I. Selection of air conditioning and refrigeration units for the clean area: The area of the clean area is approximately 1000 m², with a cleanliness level of Class 10000 (ISO Grade 7). Water-cooled screw or centrifugal refrigeration units are generally recommended; air-cooled heat pump units can also be used. Consider the following factors when making a choice: 1. The size of the cooling load (typically, the cooling load per square meter in a clean area is around 250–400 W/m², but this value needs to be determined based on actual conditions) ; 2. Temperature and humidity requirements: For Class 10000, the temperature is generally 22±2°C, with a relative humidity of around 45% to 60% ; 3. Meet all the cooling loads, including those generated by equipment inside the plant (process heat), personnel, lighting, fresh air, and heat transfer through the building’s enclosure ; 4. Take into account both the initial investment cost and the long-term energy efficiency operating costs. II. Methods for estimating the air conditioning cooling capacity in clean areas: The cooling load in clean areas generally consists of the following components: 1. Cooling load from the building envelope: The heat transfer through walls, roofs, and floors ; 2. Heat dissipation load of indoor equipment: The heat generated by the operation of production and electrical equipment is generally determined based on the equipment’s operational parameters ; 3. Lighting equipment load: Lighting power × Coefficient of simultaneous operation of equipment ; 4. Human heat dissipation load: Number of people × Heat dissipation per person (usually 75–120 W/person) ; 5. Fresh air cooling load: Fresh air volume × air density × specific enthalpy difference ; 6. Heat generated during the operation of fans, motors, etc., and other additional heat loads. Rough estimation example: In a typical CLASS10000 cleanroom, the cooling load per unit area (including equipment, lighting, personnel, building envelopes, and a certain amount of fresh air demand) is generally between 250 and 400 W/m²; a conservative value should be adopted. Estimated using the intermediate value of 350 W/m²: Cooling capacity ≈ 1000 m² × 350 W/m² = 350 kW. Taking into account a certain safety margin (usually 15%~20%): The designed cooling capacity is approximately 350 × 1.2 ≈ 420 kW. The above is a simplified estimation method; for specific projects, more detailed calculations are required to determine the cooling capacity and select an appropriate equipment capacity. .

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.