Remote IO layout

2023-05-18View Original

Thread Content

For the fine chemical production line, our management recently asked us to design on-site IO cabinets in order to reduce costs (for cables, cable trays, etc.). I’m curious to know if anyone has done or seen something like this before – is it convenient to use in practice, and are there any issues identified by experts?
Reply #22023-05-18
Remote IO stations are a very common configuration; for the relevant standards, refer to HG_T20508-2014
Reply #32023-05-19
It refers to the situation where cabinets are placed in the production workshop
Reply #42023-05-19
What is present on-site cannot be called a cabinet; the largest size for a wiring box should not exceed 1 meter, otherwise it cannot be referred to as an on-site IO
Reply #52023-05-19
Yes, we plan to make an explosion-proof box sized 600×800, which will contain terminal blocks and clips, etc. The problem this creates is that there will be many explosion-proof boxes in the workshop; therefore, I’m wondering if there are any other cases like this
Reply #62023-05-19
Some DCS manufacturers offer Smart systems, with all the components located inside explosion-proof enclosures on site; however, a single cabinet can accommodate only a limited number of sensors.
Reply #72023-05-20
It’s almost always like this; especially in refined manufacturing plants, it’s the same everywhere. It seems that Turck’s solution is a bit more focused at the moment, but it’s expensive; it can communicate with many systems. The Smatr system from the central control unit and the OCS from Lenze are quite similar in function
Reply #82023-05-20
This is a somewhat complicated issue; as safety requirements become stricter, having DCS control boxes on site might eventually pose a safety hazard, and even entire PLC cabinets are at risk. Although all of these devices meet the explosion-proof requirements, some people still consider them unsafe.
Reply #92023-05-22
Yes, we considered adopting this approach in a project a few years ago, but it was rejected. While this method saves on initial construction costs, the subsequent operation and maintenance costs might offset those savings, and there may also be a need for modifications later on, which again represents a significant expense

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.