Turnaround time: 18 hours; operation time per furnace: 9 minutes; three-stage maintenance; 5-2 sequencing; 100-hole carburizing chamber – how to plan coke pushing operations.
Reply #22019-10-18
How should the three maintenance periods be arranged appropriately?
Reply #32019-10-23
There used to be an Excel file on this topic in the forum
Reply #42019-10-24
100 divided by 3 equals 33.333, which is either 33 or 34 (the number of batches must be an integer). If it is divided into three segments, the number of batches per segment will be 33, 33, and 34 respectively. The cycle time is 18 hours; therefore, the time for each segment is 18×60÷3 = 360 minutes. The time required to produce batches in each segment is (33–1)×9 = 288 minutes; 288min ; 297 min; the maintenance time for each segment is 360 – 288 = 72 min ; 72min ; 360-297=63min

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.