What needs to be confirmed when handing over a new coal gasification project to the construction contractor?

2010-06-30View Original

Thread Content

For new coal gasification projects, when taking over the site from the construction party, what aspects need to be verified regarding the moving equipment, stationary equipment, pipelines, valves, etc.? ? 、
Reply #22010-06-30
Movable equipment must be tested during operation to ensure it functions properly. For pipes and valves, it is necessary to check whether there is any stress in the pipes and whether the pipe supports are installed correctly. Fixed equipment requires corresponding pressure test reports; if its internal structure is complex, an inspection inside the equipment is also needed. Finally, a full-scale test should be conducted to assess its performance – if everything works fine, then there should be no major issues. These are just my personal opinions for reference only
Reply #32010-07-01
China Communications Conditions 1: The project shall be completed in accordance with the design specifications; 2. The project quality is qualified ; 3. After the pressure testing of the process and power pipelines is completed, the system has been cleaned, purged, and made airtight, with insulation work largely finished ; 4. Static equipment strength testing, non-destructive testing, cleaning completed ; 5. The individual testing of the moving equipment was successful ; 6. After the load testing of large-scale units using air, nitrogen, or other media is completed, the unit’s protective interlock and alarm control systems have been successfully calibrated and tested ; 7. The electrical systems, instruments, computers, as well as the gas prevention, fire protection, and explosion prevention systems of the device have been successfully tested and calibrated ; 8. The temporary facilities in the plant area have been removed; the site is clean after work is completed and all materials have been taken away, and the vertical structure construction is finished ; 9. Complete the items related to the three inspections and four determinations that affect the joint commissioning, as well as handle any design changes; determine the completion times for the remaining tasks. CCCC-related tasks: 1. Verification and handover of the actual engineering quantities in accordance with the design specifications ; 2. Review, verification, and handover of the preliminary evaluation documents for project quality as well as relevant commissioning records ; 3. Handover of installation tools, remaining spare parts, and materials ; 4. Final project cleanup and confirmation of completion time ; 5. Handover of random technical documents ; The construction unit organizing meetings for construction, production, design, and supervision purposes serves as the mechanism for transferring responsibility for custody and use. I’m not sure if this will be useful to the original poster

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.