Dry Gas Recovery Waste Water Stripping Version – Daily Question 7.26

2017-07-26View Original

Thread Content

Multiple-choice question: The sequence for installing grounding wires is ( ). A. Install the middle phase first, then the two side phases; Install the grounding terminal first, B ; Install the conductor end first at C ; D randomly installs BC
Reply #22017-07-26
The sequence for connecting the ground wire is to first connect the ground terminal, and then the device’s conductive parts. Are you connecting both at the same time in your case? Both are first; which one is first after all?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.