This post was last edited by yuchenchf on 2017-2-15 17:26. Reward for participation: 2 wealth points. Correct reward: 8 Wealth. Multiple-choice question: In the network plan of a project, the free float of a task refers to the amount of time flexibility that can be utilized for that task without affecting ( ). A. The earliest start time of the immediate successor task B. The latest start time of the immediate successor task C. The latest completion time of the immediate successor task D. The completion time of this task A
A、Earliest start time of the immediate follow-up task
A、Earliest start time of the immediate follow-up task
In an engineering network plan, the free float of a task refers to the amount of time flexibility available for that task without affecting (A). A、Earliest start time of the immediate successor task B、Latest start time of the immediate successor task C、Latest completion time of the immediate successor task D、Completion time of this task
In an engineering network plan, the free float of a task refers to the amount of time flexibility available for that task without affecting (A). A、Earliest start time of the immediate successor task B、Latest start time of the immediate successor task C、Latest completion time of the immediate successor task D、Completion time of this task
A、Earliest start time of the immediate follow-up task