What documents does the construction contractor need to submit to the client before starting work?

2017-03-20View Original

Thread Content

After the contract is signed, what documents does the construction party need to submit to Party A? It’s my first time taking on the role of project manager, so I’m not very familiar with this. Thank you
Reply #22017-03-21
Construction organization plan, certificates of management personnel, qualification certificates for special workers (electricians, welders, scaffolders, etc.), proof of insurance coverage for workers, general layout plan of the construction site (which can be included in the construction organization plan), etc

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.