2017-12-19View Original

Thread Content

In the double-code network plan of the engineering project, the latest completion time for the concrete pouring task m is day 25, and its duration is 6 days. This task has three immediate preceding tasks: steel bar binding, formwork fabrication, and embedded part installation. Their earliest completion times are the 10th day, the 12th day, and the 13th day respectively. Therefore, the total float for task m is (  ) days.   A、6   B、9   C、12   D、15 Correct answer: A

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.