Must on-site level gauges for chemical storage tanks be equipped with double valves or plug plugs?

2018-12-18View Original

Thread Content

I have a question for everyone: Do on-site level gauges in chemical storage tanks necessarily require double valves or plug plugs? If so, which standard requires it? I would appreciate your advice.
Reply #22018-12-29
Code for Fire Protection Design of Petrochemical Enterprises GB50160-2008 7.2.8 Two drain valves shall be installed at the lowest point of combustible gas pipelines that are in continuous operation; the liquid discharged therefrom shall be sent to a closed system; For drain valves used only during startup and shutdown, a single valve can be installed along with a plug, pipe cap, blind flange, or flange cover.
Reply #32019-01-17
I’m just worried that if a valve leaks, there won’t be any way to deal with it
Reply #42020-01-19
Is 7.2.8 applicable to combustible gas pipelines with continuous operation, and to on-site level gauges?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.