What does 30% model diagram mean?

2019-01-22View Original

Thread Content

What does 30% model diagram mean?
Reply #22019-01-22
In other words, 30% of the 3D design model has been completed; at this stage there is a checkpoint where a review is conducted, primarily focusing on the positioning of the equipment.
Reply #32019-01-22
This post was last edited by The wise are enlightened on 2019-1-22 at 15:57. 30% model review (device positioning review) – Key points: 1. The positioning of all devices and the orientation of their openings; 2. Frameworks (steel and concrete frameworks) and buildings ; 3. Main operation passages and ladders ; 4. Major large-diameter pipelines or key process pipelines ; 5. Equipment and unit orientation ; 6. Reserved escape route ; 7. Pipe galleries and main pipeline support frameworks ; 8. Shape of the underground cable trench for instrument electrical systems ; 9. Space required for equipment lifting/exchanger core removal, occupied by a mobile crane.
Reply #42019-01-23
Some basic design knowledge was also learned from this. Learned: handshake
Reply #52019-12-25
Learned* it~~~~~~~~

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.