This post was last edited by 3983596_FPPZ on 2018-11-3 at 09:33. Which brother is familiar with the proper procedures for on-site installation of complete pumps? What is the sequence and process involved, and what steps need to be taken first and what later? Which tasks require inspection and supervision, and which ones need assistance from other team members? Also, please explain in detail how to conduct inspections to determine whether the installation is complete and satisfactory, including aspects such as grouting of the foundation base, level adjustment, installation of inlet and outlet pipelines as well as auxiliary pipelines, and connection of motor cables. After that, the pump can be used.
SHT3538-2017 General Specifications for the Construction and Acceptance of Petrochemical Machinery and Equipment Installation Projects, as well as API686
Thank you, this standard version can be downloaded from this forum
https://bbs.hcbbs.com/thread-2041381-1-1.html This one is for SHT3538.
In my opinion, the sequence should be: drilling holes for the base embedments – installing the pump – pouring concrete – curing – fitting inlet and outlet pipes and valves, etc. – providing support for the inlet and outlet pipes – installing additional pipelines – checking and aligning the pump – wiring the motor – testing the pump. The inspection should mainly focus on the actual operating parameters of the pump, vibration levels, bearing temperatures, noise levels, and seal leakage