What are the requirements for alignment and leveling of small centrifugal pumps (for water treatment)?

2019-12-10View Original

Thread Content

I talked to a wastewater treatment design firm today, and they said that the centrifugal pumps they supply aren’t aligned or centered. I know that both GB 50275 and the American standard API 686 specify requirements for the alignment of centrifugal pumps, but are there any different requirements for such small centrifugal pumps? For example, is centering not required? If needed, what are the reference specifications? (The flow rate of the small pump is approximately 16 cubic meters per hour, with a motor power of 4KW.) . . )
Reply #22019-12-10
See what type of centrifugal pump it is, directly connected or with a coupling. Centrifugal pumps equipped with couplings must be aligned properly
Reply #32019-12-11
This is not the responsibility of the design team; it falls under the responsibility of the construction party, with the supervisor or the project owner overseeing the inspection and acceptance.
Reply #42019-12-11
Logically, you are right. . However, I note that GB 50275 4.1.4 specifically emphasizes medium and large pumps. . So, it’s not clear whether there are any exceptions for small pumps; currently, the project plans to conduct tests in accordance with ISO 9066. . . But it’s not clear whether it can cover everything. .
Reply #52019-12-11
Proper installation of mechanical pumps requires proper alignment; many unqualified, small-scale ‘part-time’ construction teams do not understand these principles and simply consider the task complete once the pump has been fixed in place with grout. Depending on the type and size of the coupling, laser alignment or a dial indicator is used when more precise alignment is required. For some small pumps, where the couplings are of the elastic pin type or similar, it is not convenient to install a dial indicator; in such cases, where the alignment requirements are not very high, a steel ruler is usually sufficient for alignment.
Reply #62019-12-11
What you’re saying is rather lacking in sophistication; the key question now is whether it’s needed or not. What about the delivery of the design package once it’s produced? ?
Reply #72019-12-11
I think you are right. . Since it involves factory acceptance upon delivery, for producing a set of AO+MBR wastewater treatment equipment, it is still under consideration at the research center to determine what specific aspects need to be checked
Reply #82019-12-11
Haha, it’s probably because domestic manufacturers have become too complacent. .
Reply #92019-12-11
Your problem lies in the acceptance criteria. During acceptance, inspection shall be carried out in accordance with the alignment requirements specified in the equipment’s user manual; if no such standards are available, inspections can be conducted based on relevant standards. As long as the equipment operates properly and no issues arise during the warranty period, it is considered acceptable. All of this is stipulated in the contract. If it is beyond the scope of the contract, a request for technical changes should be submitted. For these types of small water pumps, just use half a piece of steel saw blade and press it against them, leaving an appropriate gap; once that’s done, the pump should start working right away. The key is that it is considered accepted as long as there are no issues during the usage period.
Reply #102019-12-12
The factory conducts online tests before the products leave the facility; it is possible to send personnel to attend these tests and inspections, in order to determine whether the pump meets the design and operational requirements based on parameters such as vibration, temperature, and operating conditions. After leaving the factory and undergoing transportation, a visual inspection upon arrival at the site showed no dents, rust, or damage. On-site installation was completed with no issues regarding alignment or centering; commissioning proceeded without problems. Acceptance was finalized, and the equipment entered its operational warranty period.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.