Segmental lifting of the crude hydrogenation unit’s fractionation tower for the Xinte Special Approved East Silicon-based New Materials Project

2022-12-27View Original

Thread Content

On November 5, 2022, the lower section of the crude separation column for the cryogenic hydrogenation unit in the Xintezhundong silicon-based new materials project was successfully installed. The equipment is 40.14 meters tall, 4.6 meters in diameter, and weighs 255 tons. It was lifted into place safely and efficiently using a 1250-ton crawler crane as the main lifting device, with a 400-ton crawler crane assisting in guiding it. The project is located in the Zhundong Economic and Technological Development Zone in Changji Prefecture, Xinjiang. Its main components include polycrystalline silicon production facilities, accompanying chlor-alkali plants, utility facilities, and auxiliary production facilities.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.