All 4 core substations of Huajin Amei have successfully received power supply

2025-11-16View Original

Thread Content

On November 11, with the successful initial power supply to the 110kV substation in the chemical processing area of the Huajin AAME fine chemicals and raw materials project, all 4 core substations of the project – 1 220kV main substation and 3 110kV substations – have been powered up and put into operation, thus completing the integration of the project’s power supply network. As the power hub of the project, the 4 core substations bear the key responsibility of providing stable and reliable power supply to all the project’s production facilities and auxiliary systems. The 220kV main substation serves as the energy hub of the project, responsible for coordinating the receipt and distribution of electricity. The 3 110kV substations cover the refining area, the chemical industry area, and the utility area respectively, creating a reliable power supply system based on a main grid backbone with regional power supply units. The 110kV substation in the chemical industry zone that has been successfully put into operation, together with the 220kV main substation that was already in use earlier, the two 110kV substations, as well as some 35kV and 10kV substations, now provides the necessary conditions to ensure a seamless power supply to the project’s facilities. This will offer solid power support for subsequent tasks such as equipment installation and commissioning, as well as trial production, thus accelerating the process of completing and bringing the project online.
Reply #22025-11-16
As the power hub of the project, the 4 core substations bear the key responsibility of providing stable and reliable power supply to all the project’s production facilities and auxiliary systems. The 220kV main substation serves as the energy hub of the project, responsible for coordinating the receipt and distribution of electricity. The 3 110kV substations cover the refining area, the chemical industry area, and the utility area respectively, creating a reliable power supply system based on a main grid backbone with regional power supply units. The 110kV substation in the chemical industry zone that has been successfully put into operation, together with the 220kV main substation that was already in use earlier, the two 110kV substations, as well as some 35kV and 10kV substations, now provides the necessary conditions to ensure a seamless power supply to the project’s facilities. This will offer solid power support for subsequent tasks such as equipment installation and commissioning, as well as trial production, thus accelerating the process of completing and bringing the project online. The Panjin Huajin Amei Fine Chemicals and Raw Materials Project has a total investment of 83.7 billion yuan. It is a major project under the China-Saudi Arabia Belt and Road Initiative, and it has been included in the relevant plans. It constitutes an important part of China North Industries Group’s efforts to develop the oil and petrochemical industry chain, and it is also key to Panjin’s goal of becoming a significant national hub for the petrochemical and fine chemical industries. The project is located in the Liaobin Coastal Economic and Technological Development Zone in Panjin City, Liaoning Province, covering an area of 8.9 square kilometers; completion of the mechanical construction is expected by 2025. The refining section includes: 20 process units in total, such as a newly built atmospheric and vacuum distillation unit with an annual capacity of 15 million tons, a light hydrocarbons recovery unit, a coal diesel hydrocracking unit, a diesel hydrocracking unit, a wax oil hydrocracking unit, a residue hydrorefining unit, a residue catalytic cracking unit, a high-propylene catalytic cracking unit, a gasoline desulfurization unit, an aromatic compounds complexing unit (including p-xylene), a gas refining unit, a gas fractionation unit, a C2 recovery unit, a PSA unit, a coal-to-hydrogen unit, a synthetic ammonia unit, a methanol unit, an acidic water stripping unit, a solvent regeneration unit, and a sulfur recovery unit. The chemical processing section includes: 1 new steam cracking unit with a capacity of 1.5 million tons per year (taking into account the ethylene recovered from various units, this results in an ethylene production capacity of 1.63 million tons per year), a hexene-1 unit, an ethylene glycol unit, an ethylbenzene/styrene unit, a high-density polyethylene (HDPE) unit, a full-density polyethylene (FDPE) unit, 3 polypropylene (PP) units, an acrylonitrile unit, an MMA unit, an ABS unit, a butadiene extraction unit, a C4 complex, and a cracked gasoline hydrogenation complex – totaling 15 process units
Reply #32025-11-16
【Ten Years of Rapid Development in Chemical Equipment】2823-2025: Zhejiang Xinhecheng becomes the third company in the world to master the technology for producing bio-based PPS products. https://bbs.hcbbs.com/thread-5705209-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #42025-11-17
【Common Issues in Haichuan Pipeline Design】Proper consideration should be given to the space required for equipment maintenance and the operation of valves. https://bbs.hcbbs.com/thread-5705460-1-1.html (Source: Haichuan Chemical Forum)
Reply #52025-11-17
【Ten Years of Rapid Development in Chemical Engineering Equipment】China’s largest “carbon capture” project: Successful trial injection of carbon dioxide in Yulin’s 4 million-ton capacity “carbon capture” project 28262025 https://bbs.hcbbs.com/thread-5705257-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #62025-11-17
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2027 to 2025, the Three Gorges Group’s Ulanqab \"integration of power generation, transmission, consumption, and storage\" test base successfully produced liquid hydrogen. https://bbs.hcbbs.com/thread-5705274-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #72025-11-18
【Ten Years of Rapid Development in Chemical Processing Equipment】Delivery of the first modular submerged combustion vaporizer (SCV) unit in China that utilizes a floating storage and regasification unit (FSRU), 2828–2025 https://bbs.hcbbs.com/thread-5705393-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #82025-11-18
【Ten Years of Rapid Development in Chemical Engineering Equipment】China-made desalination modules for European methanol projects were officially delivered and shipped, 2029–2025 https://bbs.hcbbs.com/thread-5705395-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #92025-11-19
【Ten Years of Rapid Development in Chemical Engineering Equipment】Successful assembly of the DC converter transformer for the world’s first \"sea-land integrated\" flexible DC transmission project from 2025 to 2030 https://bbs.hcbbs.com/thread-5705493-1-1.html (Source: Haichuan Chemical Engineering Forum)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.