The main structure of the extrusion granulation plant, a key facility in Zhejiang Yuanjin New Materials Co., Ltd.’s integrated project for the comprehensive utilization of alkane resources – featuring 2×300,000 tons per year polypropylene production capacity – has been successfully completed

2026-03-22View Original

Thread Content

In mid-March 2026, an important construction milestone was reached for the integrated project for the comprehensive utilization of alkane resources at Zhejiang Yuanjin New Materials Co., Ltd. The main structure of the extrusion granulation plant, the core facility of the 2×300,000 tons/year polypropylene plant constructed by the Shanghai branch of China National Chemical Engineering Third Construction Co., Ltd., has been successfully completed, marking a significant milestone in the construction of this plant. As a key production facility in the polypropylene plant, the extrusion granulation building, whose construction was completed recently, features a frame-type structural design. It has 5 floors in total and an architectural height of 41 meters, presenting challenges such as a high degree of structural complexity and difficulties in vertical construction. Key milestone review: On the afternoon of March 5, the company held a mobilization meeting at the project site to launch a 200-day intensive effort to ensure completion of the project by October 31. Construction and management units such as Sinochem Second Construction Group Co., Ltd., China National Chemical Engineering Corporation Third Construction Company, China National Chemical Engineering Corporation Thirteenth Construction Company, China National Chemical Engineering Corporation Sixteenth Construction Company, and Qilu Petrochemical Engineering Co., Ltd. attended the meeting. The meeting set the goal of achieving full completion by October 31, assigned tasks for two phases of effort, and launched a labor competition titled the \"100-Day Campaign\" from March 15 to June 30.
Reply #22026-03-22
On September 17, 2025, the propane dehydrogenation unit of Phase I of the Shangyu Alkanes Resource Comprehensive Utilization Project completed the lifting of 10 large-scale equipment items, including the heat integration units 11E-0101A/B, 4 reactors in the reaction unit, and 4 catalyst collectors. The total weight of the equipment to be lifted was 1,213 tons; the net weight of the 11R-01044# reactor unit alone was 257 tons. The lifting operation was a complete success. During the lifting process, the company coordinated closely with the PMC and supervision unit to ensure proper oversight; the construction team organized the work in an orderly manner with sound planning, completing the lifting task 5 days ahead of the scheduled deadline. The 750,000 tons per year propane dehydrogenation unit is the main facility in Zhejiang Yuanjin New Materials’ integrated project for the comprehensive utilization of alkane resources (Phase I). The investment planned for Phase I amounts to 11 billion yuan. In addition to two propane dehydrogenation units capable of producing 750,000 tons of propylene each, the project also includes three polypropylene production units with a combined capacity of 1.25 million tons, one hydrogen peroxide production unit with a capacity of 400,000 tons, and one propylene oxide production unit using the direct oxidation method with a capacity of 300,000 tons. Additionally, 80,000 tons of hydrogen will be produced as a by-product.
Reply #32026-03-22
【Ten Years of Rapid Development in Chemical Engineering Equipment】The first domestically developed third-generation nuclear power steam release isolation valve for the \"Hualong One\" reactor, model 3045-2026, has been officially shipped. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716068 (Source: Haichuan Chemical Engineering Forum (HCBBS))
Reply #42026-03-24
【HaiChuan Equipment Guessing Game】==What a big ice cream! https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716191 (Source: HaiChuan Chemical Forum (HuaHaiChuanLiu hcbbs))
Reply #52026-03-25
【Ten Years of Rapid Development in Chemical Equipment】3050-2026: A period of 15 years! The world’s first polyether plant capable of stable operation at low temperature and pressure to produce 80,000 tons of carbon dioxide has been successfully put into production. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716103 (Source: HaiChuan Chemical Industry Forum (HuaHaiChuanLiu hcbbs))
Reply #62026-03-27
【Ten Years of Rapid Development in Chemical Equipment】Key dehydrogenation technologies for the toluene-methylcyclohexane organic liquid hydrogen storage system from 2030 to 2026 have been validated. https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716272 (Source: Haichuan Chemical Industry Forum (HCBBS))
Reply #72026-03-28
【Ten Years of Rapid Development in Chemical Engineering Equipment】3052-2026: Dongfang Electric’s natural gas-ammonia combustion technology has achieved successful pilot-scale testing! https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716290 (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))
Reply #82026-03-29
【Common Issues in Haichuan Pipeline Design】--How to open and maintain valves that are crowded together? ? https://bbs.hcbbs.com/forum.php?mod=viewthread&tid=5716525 (Source: Haichuan Chemical Industry Forum (Hua Haichuan Liu hcbbs))

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.