Installation of key large-scale equipment exceeding 1,000 tons for the 300,000 tons/year PEO production facility in Rongsheng New Materials project completed
Thread Content
On January 6, 2026, a significant milestone was reached at the Rongsheng New Materials project’s 300,000 tons per year PEO production facility: all four key large-scale equipment units within the 10A reaction framework were safely and precisely installed, marking the official conclusion of the equipment installation phase of the project. The four pieces of equipment lifted in this batch are core components of the plant’s process flow, and their successful lifting marks a milestone for the entire project. The reactor/gas cooler (1225-R-0110) has a net weight of 1,063 tons, making it the heaviest single piece of equipment in the facility at present; its installation elevation is 20.85 meters. Reactor gas cooler drum (1225-V-0110), weighing 232 tons. The reactor gas cooler drum (1225-V-0112) weighs 120 tons and has an installation height of 18.15 meters. Gas-to-gas heat exchanger (1225-E-0111), weighing 216 tons. Among them, the lifting of the reactor gas cooler drum (1225-V-0112) was the most technically challenging and complex aspect to coordinate in this operation. The device must be precisely placed on a specific base inside the frame; the space is limited and the paths are circuitous. Through precise calculations and simulations, the project team developed an innovative solution of \"lifting with two machines and pulling within the frame\": first, a 1600-ton crawler crane is used to lift it to the specified height at the edge of the frame. Subsequently, with the coordinated effort of 280-ton crawler cranes, a relay delivery process was carried out to smoothly transfer the equipment onto the specially prepared fixtures. Finally, the construction workers used multiple sets of large winches for precise pulling and adjustment; akin to threading a needle, they slowly moved this 120-ton \"giant\" onto the equipment foundation at a height of 18.15 meters, achieving placement with millimeter-level accuracy. The entire process is a model example of precise indoor installation of large-scale equipment.Construction unit: Rongsheng New Materials (Zhoushan) Co., Ltd.
Construction location: Jintang Island, Dinghai District, Zhoushan City
Total investment: 76 billion yuan
Construction contents: Construction of new production facilities including a 600,000-ton/year propane dehydrogenation unit, a 3 million tons/year catalytic cracking unit, a 1 million tons/year gas separation unit, a 600,000-ton/year aromatic extraction complex, a 300,000-ton/year PEO production unit, a 1 million tons/year EVA complex, a 200,000-ton/year POE production unit, 400,000/250,000-ton/year phenol production units, a 200,000-ton/year 1,3-propanediol production unit, 400,000/880,000-ton/year PO/SM production units, a 400,000-ton/year PTT production unit, a 500,000-ton/year isobutane normalization unit, a 600,000-ton/year maleic anhydride production unit, a 500,000-ton/year BDO production unit, a 200,000-ton/year PBS production unit, a 400,000-ton/year PBT production unit, a 120,000-ton/year isobutylene production unit, a 180,000-ton/year butene oxidation dehydrogenation unit, a 150,000-ton/year CO₂ recovery unit, a 160,000-ton/year ethoxylation unit, a 200,000-ton/year DMC production unit, a 480,000-ton/year polyether polyol production unit, a 1.2 million tons/year ABS production unit, 2×240,000-ton/year bisphenol A production units, 2×260,000-ton/year polycarbonate production units, a 100,000-ton/year CHDM production unit, a 100,000-ton/year PCT production unit, a 100,000-ton/year PCTG production unit, a 50,000-ton/year UHMWPE production unit, 2×450,000-ton/year PP production units, a 300,000-ton/year α-olefin production unit, a 600,000-ton/year polyurethane elastomer production unit, a 140,000 standard cubic meters/hour coal-to-hydrogen production unit, and 2×20,000-ton/year sulfuric acid production units.