Issues with land use certificates

2015-06-03View Original

Thread Content

May I ask, in the approval process for chemical industry projects, which comes first: the Land Use Certificate or the Construction Land Planning Permit? Is a \"Construction Land Planning Permit\" required to obtain a \"Land Use Certificate\"?
Reply #22015-07-02
The \"Construction Land Planning Permit\" can be obtained first, followed by the \"Pre-examination of Land Use\"; A Land Use Permit does not necessarily require a Construction Land Planning Permit; you can check the procedures at the local government service center.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.