Is there anyone from Zhongtian Hechuang who works on polyolefin plants, or someone you know? Please leave your contact information, thank you
Why? Something wrong? Zhongtian has a total of three sets of polyethylene fabric
:) It is said that construction will start next July, and the benefits seem attractive; I’m not sure what the actual situation is like
This post was last edited by jordan569 on 2015-8-28 16:08. I went there; it’s a pretty large project. However, it is quite far from each of the surrounding urban areas.
The project was rushed into, but the necessary approvals were not obtained, nor were any bank loans secured; as a result, a large amount of money owed to the contractors remained unpaid, creating a situation of great distress.
Has polyethylene already been produced in finished form?
It can’t be that tragic! Wasn’t it said that all the funds have been secured? ~:L
Is SEI the general contractor for Zhongtian? What is the relationship between Zhongtian He SEI and Sinopec? I don’t understand! Do China Coal and the remaining shareholders not pay any money? Do you keep working even when you owe money? It seems that the plan to start production by Zhongtian next year is just hype? **Zhongtian is not among the 10 coal chemical projects approved by the National Development and Reform Commission; I only found out about this today!
The project has not yet been approved, so it’s difficult to obtain loans, and migrant workers are blocking the doors every day!
The promotion is really on a high level – don’t they have plenty of money?