Let’s discuss what kinds of tests are primarily referred to as the verification and supplementary testing of pipeline components in SH3503 Not very clear
Reply #22015-06-24
This one, I guess, was copied from ASME B31.3. . Verification tests mainly involve type tests conducted through blasting. Supplementary inspections are those inspections that take place in addition to the mandatory inspections. For example, for that weld seam where 100% RT is required, then you need to carry out a surface inspection. .
Reply #32015-06-24
For example, alloy steel undergoes spectral testing, namely PMI, while low-temperature fittings are subject to low-temperature impact testing

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.