What percentage do the instrumentation and DCS systems account for in the total cost of the project?

2015-07-02View Original

Thread Content

In a coal-to-oil project, what is the proportion of the costs associated with instruments and DCS systems in the total cost of the project?
Reply #22015-07-02
Are there any regulations regarding this as well? Our factory’s total investment in 5Y instruments is only 300 watts
Reply #32015-07-02
Three million seems a bit low. Where is DCS located, and how many points are there?
Reply #42015-07-02
There are not many I/O points; they are from Zhejiang University’s Central Control system, and the details haven’t been finalized yet. I saw that the total cost for the instrumentation contracts is over 3 million yuan, while the cost for the DCS system is only 300,000 yuan. The problem is that there are very few I/O points – there are only two cabinets. We plan to add a spare cabinet as well as a power supply cabinet
Reply #52015-07-02
Based on DCS prices, your control points should be around 500 points. Your instrumentation contract doesn’t include important valves, right? Some valves, especially imported ones, are quite expensive.
Reply #62015-07-02
I’m sorry; it includes all the instruments along with the cables. The instruments used throughout the factory were not procured through a bidding process – they were supplied by Jinhu Hongguang Instruments, a company affiliated with Su Yi Group. You know how it is
Reply #72015-07-02
That’s quite cheap. If you’re responsible for the maintenance of the instruments in the future, you’ll need to pay closer attention during construction and commissioning
Reply #82015-07-02
To be honest, I wouldn’t have left if I hadn’t found a place to work. The small factory moved here from Jiangyin, and its operators were brought from there as well. Previously, the company didn’t have any personnel specialized in instrumentation; now, however, chemical companies are required to have automated control systems, which is why they hired us two. But we’re only responsible for the technical aspects – no one else listens to us. Everyone, from the boss down to the employees, thinks that instrumentation is just a waste of money, something meant only to meet regulatory requirements as a form of decoration.
Reply #92015-07-02
Our project costs 100 million, and the DCS control system costs over 3 million, not including instruments and power distribution.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.