【Daily Question】2015.08.08 Non-destructive testing of steel materials prone to delayed cracking (2 wealth points for a reply; +3–8 wealth points if the answer is correct)

2015-08-08View Original

Thread Content

This post was last edited by FORREST_GUMP on 2015-8-8 09:36. The Mechanical Section has introduced the \"Question of the Day\" feature, which aims to foster an active atmosphere for technical discussions and guide the direction of such exchanges. It also provides users with financial rewards, helping them experience various cool features. Fill-in-the-blank: For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least ( ) hours after welding is completed. Please note: We will close this thread after 24 hours, and at that time we will announce the best reply (the best assistance), as well as the answer and explanation. Charisma Reward: Those who post a topic in this section within two days to provide a detailed explanation or discussion of the knowledge points related to this question are asked to reply/comments in this post to inform us, and we will award them charisma points. It is not allowed to simply copy and paste; original content is preferred, with at least some organization by the user along with personal insights and opinions. After registration, we will rank based on the content of the posts: the last-place contestant will receive +1 charm, the second-to-last +2 charm, and so on, with the highest score earning +5 charm. http://bbs.hcbbs.com/thread-1381938-1-1.html Earning wealth by inviting friends http://bbs.hcbbs.com/thread-1389240-1-1.html [Mechanical Section] Collection of essential knowledge 【Seeking manufacturer sponsorship】 (long-term campaign)
Reply #22015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #32015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (24) hours after welding is completed.
Reply #42015-08-08
36 hours. . There is still a difference from 150; 150 specifies 24 hours, while for spherical tanks it is 36 hours
Reply #52015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #62015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (24) hours after welding is completed.
Reply #72015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #82015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #92015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #102015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.
Reply #112015-08-08
For spherical tanks manufactured from steel prone to delayed cracking, non-destructive testing of the welds shall be carried out at least (36) hours after welding is completed.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.