Welding issues after heat treatment

2015-08-09View Original

Thread Content

There is a piece of equipment on site; the material used is 14Cr1MoR with a thickness of 130 mm. It has already been delivered to the site. The manufacturer failed to weld the pre-welded parts. I would like to ask what considerations need to be taken into account regarding the welding process and heat treatment process for welding such equipment’s pre-welded parts
Reply #22015-08-09
Preheat before welding, and carry out heat treatment immediately after welding; the specific procedures can be followed as specified in the design documents or welding standards Nbt 47014 and 47015
Reply #32015-08-09
Preheating, inspection, welding, post-heat treatment, non-destructive testing
Reply #42015-08-12
This works too. . . This manufacturing plant is really amazing. . . The first two points mentioned are quite correct.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.