A project under design requires the installation of drain valves between the control valve and the isolation shut-off valve; in other words, drain valves are to be placed before and after the control valve. Is it necessary to install drain valves before and after the control valve on the instrument? Are there any regulatory standards that explicitly require this design?
Reply #22015-08-21
Previously, vent valves were usually installed only in front of control valves, and those control valves were mostly of the type with low inlet and high outlet. Nowadays, more control valves of the type with high inlet and low outlet are being used, but design conventions have not changed. For hazardous media that require complete displacement, especially those for which the displacement medium has too low pressure to enter the system, we install vent valves before and after the control valve.
Reply #32015-08-21
It is not necessary to install drain valves separately before and after the control valve
Reply #42015-08-23
For FC valves, they are installed on both the front and back; for FO valves, only the front one is installed. That’s what UOP stipulates.
Reply #52015-08-26
Assume that the drainage method is used in practice for the convenience of valve maintenance, under the following circumstances: 1. Pressure relief is required; 2. Hazardous gases or liquids ; 3. Rinse.
Reply #62015-08-26
SH/T 3012-2011 Code for Design of Metal Piping Layout in Petrochemical Industries
Reply #72015-08-26
Could you explain it in more detail? Is there a standard basis?
Reply #82015-08-26
Is it necessary to install a drain valve at the inlet of the safety valve?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.