Should the crew’s accumulator be repressurized while the oil is in circulation, or after the machine has stopped and all oil has been returned?

2015-09-16View Original

Thread Content

The major maintenance at our factory is coming to an end. While checking the accumulators before the oil is circulated again, it was found that one of them had low pressure. When trying to replenish the pressure, one of the technicians strongly advised that it would be better to do this once there is oil around the air bag during the oil circulation process. Since the machine has been shut down for over half a month, all the oil has returned to the tank; as a result, there is a lack of liquid inside. Replenishing the pressure forcefully can harm the lifespan of the air bag and may cause it to get damaged. I’m very confused and would like to ask how everyone usually handles this, especially what the reason behind it is It seems like there’s oil around when the system is in operation; the pressure charging might not be accurate. The pressure should reflect the system’s oil pressure, and it shouldn’t have much to do with the airbags. Or maybe it’s sufficient as long as there’s oil around the airbags. It doesn’t seem that complicated, really. I’m seeking advice here~ Thank you:handshake
Reply #22015-09-16
After servicing the unit, check the accumulator pressure; if it is low, top it up – this has always been the procedure; I’ve never heard that not charging the air tank is bad for the airbags. As you said, if there is already pressure in the pipeline, and then nitrogen is added to increase the pressure, this affects the accuracy of the nitrogen pressure reading. This is my personal opinion.
Reply #32015-09-16
Online working accumulators can be inflated to restore pressure without affecting the normal operation of the equipment
Reply #42015-09-16
The last edit to this post was made by zhangya*ong on 2015-9-16 at 21:56. The requirement for charging the accumulator in the unit’s oil system is to open the inlet valve of the accumulator after the oil has been circulated; fill it with approximately 1/10 of the accumulator’s capacity, then close the shut-off valve, and finally charge the accumulator. This approach provides some protection for the accumulator’s bladder.
Reply #52015-09-17
After the oil system is shut down, check the accumulator pressure; it should normally be maintained at 60-70% of the supply oil pressure, which is what I do.
Reply #62015-09-17
If it is operating online and the accumulator already has the required oil pressure, how can the pressure be increased? How much and when should it be replenished? If the isolation accumulator is isolated, how can the pressure already present inside it be released?
Reply #72015-09-17
I did find that phrase when searching online; it seems to make sense after all
Reply #82015-09-17
The accumulator should be equipped with a sight glass featuring an oil level gauge, as well as a filling valve; if the oil level exceeds the specified limit, the filling valve can be used to lower the oil level in the accumulator back to the normal range.
Reply #92015-09-18
:'(Leave a mark first to see other opinions from the experts)
Reply #102015-09-20
Hehe, Bado watched for a while and learned a lot of useful things.
Reply #112015-09-21
Close the valves of the accumulator and oil pipes, then open the pressure relief valve to release any remaining oil pressure

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.