This post was last edited by yuchenchf on 2015-10-17 at 11:58. Reward for participation: 2 Wealth. Reward for correct answer: 9 wealth. There is one construction machine at the construction site; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for idle time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were wasted, so the construction company can claim ( ) yuan in compensation. A.0 B.500 C.1000 D.1500 Answer ; D 【Production and Management Division】Seeking moderators and technical discussants to join
There is one construction machine at the construction site; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for idle time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were lost, so the construction company can claim (D) yuan in compensation. A.0 B.500 C.1000 D.1500
There is one construction machine at the construction site; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for idle time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were lost, so the construction company can claim (D) yuan in compensation. A.0 B.500 C.1000 D.1500
There is one construction machine at the construction site; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for idle time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were wasted, so the construction company can claim (A) yuan in compensation. A.0
At the construction site, there is one construction machine; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for lost time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were wasted, so the construction company can claim ( ) yuan in compensation. A.0 B.500 C.1000 D.1500
B--------------------------------
B--------------------------------
Construction companies can claim (1500) yuan
There is one construction machine at the construction site; the unit cost per shift is 1,000 yuan per shift, with a depreciation cost of 500 yuan per shift. The daily wage for labor is 100 yuan per workday, and there is a compensation of 50 yuan per workday for idle time. Due to a power outage in the grid, work was halted for 2 days and 10 man-days were wasted, so the construction company can claim (A) yuan in compensation.
The answer is D.....................