Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is ( ). A,2 B.3 C.4 D.5 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-10-15
In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is (C 4). A,2 B.3 C.4 D.5
Reply #32015-10-15
In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is (A).
Reply #42015-10-15
In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is (A).
Reply #52015-10-15
In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is (B)
Reply #62015-10-15
A-----------------------------------
Reply #72015-10-15
A-----------------------------------
Reply #82015-10-15
When an intermediate station in a long-distance pipeline with closed transportation stops operating due to some reason, the inlet and outlet pressures at all stations located before that stopped station remain (B). A. Decrease B. Increase C. Remain unchanged D. Cannot be determined. In a certain network plan, the earliest completion time for task M is day 8, and the latest completion time is day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float for this task is (B). A,2 B.3 C.4 D.5
Reply #92015-10-15
The answer is A......................................
Reply #102015-10-15
In a certain network plan, task M has an earliest completion time of day 8 and a latest completion time of day 13. The duration of this task is 4 days, and the minimum value of the time intervals with all its immediate successors is 2 days. Then the free float of this task is (A,2). The minimum interval between task M and all subsequent tasks is 2 days, so the free float is 2 days.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.