Let’s work on question 24, part 2015, from the First-Class Constructor Examination – Multiple Choice Questions 19-20 in Engineering Economics

2015-10-25View Original

Thread Content

I have gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to increase everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give a reward for correct answers. ****************************************** 19. A construction company intends to lease a piece of equipment from a leasing company. The price of the equipment is 1.2 million yuan, the lease period is 6 years, with payments made at the end of each year. The discount rate is 10%, and the surcharge rate is 4%. Calculated using the additional rate method, the rent payable is 10,000 yuan. A.25.0 B.27.5 C.33.5 D.36.8 Answer: D 【Expert Explanation】This explanation: Use the formula for calculating rent based on the additional rate method. 20. For construction drawing budgets with particularly unique design schemes, for which there are no comparable projects available, and where high accuracy in review is required, the appropriate method of review is. A. Comprehensive review method B. Standard budget review method C. Comparative review method D. Focused review method 【Answer】A 【Expert explanation】The three sentences in this question tell us the answer ; It is special in nature, so there are no standard drawings; therefore, option B is excluded. Since there are no similar projects, option C is also excluded. The precision requirements for review are high, so option D is excluded as well ; Don’t look up in the book; there are no answers in it.
Reply #22015-10-25
19、D---------------20、A
Reply #32015-10-25
19. The construction company intends to lease a piece of equipment from a leasing company; the price of the equipment is 1.2 million yuan, the lease term is 6 years, the rent is paid at the end of each year, the discount rate is 10%, and the surcharge rate is 4%. Calculated using the additional rate method, the rent payable is 10,000 yuan. D A.25.0 B.27.5 C.33.5 D.36.8 20. For construction drawing budgets whose design schemes are particularly special, with no similar projects available for comparison and high accuracy requirements for review, the appropriate method of review is. A. Comprehensive review method B. Standard budget review method C. Comparative review method D. Focus review method
Reply #42015-10-25
19, D. ---------20, A-----------------
Reply #52015-10-25
D.36.8 A. Comprehensive review method
Reply #62015-10-25
19. The construction company intends to lease a piece of equipment from a leasing company; the price of the equipment is 1.2 million yuan, the lease term is 6 years, the rent is paid at the end of each year, the discount rate is 10%, and the surcharge rate is 4%. Calculated using the additional rate method, the rent payable is 10,000 yuan. D A.25.0 B.27.5 C.33.5 D.36.8 20. For construction drawing budgets whose design schemes are particularly special, with no similar projects available for comparison and high accuracy requirements for review, the appropriate method of review is. A. Comprehensive review method B. Standard budget review method C. Comparative review method D. Focus review method
Reply #72015-10-25
19. The construction company intends to lease a piece of equipment from a leasing company; the price of the equipment is 1.2 million yuan, the lease term is 6 years, the rent is paid at the end of each year, the discount rate is 10%, and the surcharge rate is 4%. Calculated using the additional rate method, the rent payable is 10,000 yuan. D A.25.0 B.27.5 C.33.5 D.36.8 20. For construction drawing budgets whose design schemes are particularly special, with no similar projects available for comparison and high accuracy requirements for review, the appropriate method of review is. A. Comprehensive review method B. Standard budget review method C. Comparative review method D. Focus review method
Reply #82015-10-25
19. The construction company intends to lease a piece of equipment from a leasing company; the price of the equipment is 1.2 million yuan, the lease term is 6 years, the rent is paid at the end of each year, the discount rate is 10%, and the surcharge rate is 4%. Calculated using the additional rate method, the rent payable is 10,000 yuan. A.25.0 B.27.5 C.33.5 D.36.8 Answer: D. 20. For construction drawings budgets whose design is quite special, with no similar projects available for comparison and high accuracy requirements for review, the appropriate method of review is. A. Comprehensive review method B. Standard budget review method C. Comparative review method D. Focus review method Choose A
Reply #92015-10-25
19. D.36.8 20. A. Comprehensive review method
Reply #102015-10-25
The answer is D/A.......................................

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.