Let’s work on Questions 30-2 from the 2015 First-Class Constructor Examination – Multiple Choice Questions 33-34 in \"Engineering Economics\"; there will be a reward for correct answers

2015-10-28View Original

Thread Content

I’ve gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to boost everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give a reward to those who give correct answers. ****************************************** 33. Regarding the bidding prices submitted by bidders under the bill of quantities bidding method, which statement is correct? A. The price of the specialized works included in the provisional estimate for specialized works should be determined by the bidder themselves and included in the bid price. B. The materials listed in the provisional estimate should be included in the comprehensive unit price at the provisional unit price. C. The total price items under the measure items should include fees and taxes. D. Bidders can offer a certain degree of discount on the total price when submitting their bids. Answer: B 【Expert Explanation】Explanation: The provisional estimate for specialized works is filled in according to the amount specified by the tenderer; therefore, option A is incorrect ; The total price items in the measure items should include all items except for regulatory fees and taxes; therefore, C is incorrect ; The bid price cannot reduce the total amount, so D is incorrect. 34. A company has four options for cash management, and the best option for maintaining an optimal cash balance is Option X. A. A B. B C. C D. D Answer: C 【Expert Explanation】The optimal cash holding level is the option that results in the lowest total cost. By adding up the three types of costs for each option, option C has the lowest total cost; therefore, the answer is C.
Reply #22015-10-28
33. Regarding the bids submitted by bidders under the bill of quantities tendering method, which statement is correct? (B) A. For the specialized works included in the provisional estimate for specialized projects, the bidder shall determine the price themselves and include it in the bid amount. B. The materials listed in the provisional estimate should be included in the comprehensive unit price at the provisional unit price. C. The total cost items related to measure items should cover regulatory fees and taxes. D. Bidders may offer a certain percentage discount on the total cost when submitting their bids. 34. There are four options available for a company’s cash management, and the best option for determining the optimal cash holding level is option (C). A. A B. B C. C D. D
Reply #32015-10-28
33、B------------------------------------34、
Reply #42015-10-28
Regarding the bid prices submitted by bidders under the bill of quantities bidding method, the following statement is correct. (B) For a company’s cash management, four options are available, and the optimal cash holding level corresponds to Option. ( C )
Reply #52015-10-28
33-D...............................
Reply #62015-10-28
33. Regarding the bids submitted by bidders under the bill of quantities tendering method, which statement is correct? (B) A. The costs related to the specialized works included in the provisional estimate for specialized works should be determined by the bidder themselves and included in the bid price. B. The materials listed in the provisional estimate should be included in the comprehensive unit price at their provisional unit prices. C. The total amounts for the measure items should include fees and taxes. D. Bidders may offer a certain percentage discount on the total price when submitting their bids. 34. There are four options available for a company’s cash management, and the best option regarding the optimal cash holding level is Option X. (C) A. A B. B C. C D. D
Reply #72015-10-28
33. B: The materials included in the provisional estimate should be accounted for in the comprehensive unit price at the provisional unit price. 34. C: C.
Reply #82015-10-28
C. The total price items in the measure items should include fees and taxes——I think this is correct
Reply #92015-10-28
33、B 34、The questions are incomplete; there is no solution
Reply #102015-10-28
B. The materials included in the provisional estimate should be accounted for in the comprehensive unit price at the provisional unit price

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.