Those who come to do exercises on Sundays are all good comrades! ! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png I’ve gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give rewards for correct answers. ******************************************54. According to the \"Code for Valuation of Construction Projects\" (CB505000-2013), in the bidding quotes for construction projects, which item cannot be considered a competitive cost? A. General contracting service fee B. Additional cost for night work C. Cost of individual construction tasks D. Regulatory fees. Answer: D 【Expert explanation】This question tests knowledge of the method of valuation based on bill of quantities. The costs related to safe and civilized construction, as well as various fees and taxes, shall be calculated in accordance with ** or the regulations set by provincial or industry-specific construction authorities; they cannot be considered competitive expenses. Refer to page P23955 of the textbook. According to the \"Code for Engineering Quantity Calculation in Construction Projects\" (CB505000-2013), when preparing the bill of quantities, the labor costs listed in the daily wage table should be itemized. A. Type of work B. Professional title C. Position D. Technical level Answer: A 【Expert explanation】This question relates to the preparation of other item lists. When preparing a quantity list, the labor costs in the daily wage table should be listed in detail by type of work, while materials and machinery should be listed in detail by specifications and models. See page P231 of the textbook.
54, D————–——–55, A. --------------
According to the \"Code for Engineering Cost Calculation in Construction Projects\" (CB505000-2013), in the bid prices for construction projects, the item that cannot be considered as a competitive cost is D. Regulatory fees
55. In accordance with the \"Code for Engineering Quantity Calculation in Construction Projects\" (CB505000-2013), when preparing the bill of quantities, the labor costs listed in the daily rate table should be itemized. A. Job type
54. D. Fees 55 A. Job types
C. Cost of individual construction tasks; A. Job type
Is choosing D the correct answer for this question? It has to be a character
54. According to the \"Code for Valuation of Construction Projects\" (CB505000-2013), in the bidding quotes for construction projects, the item that cannot be considered a competitive cost is (D). A. General contracting service fee B. Additional cost for night work C. Cost of individual construction tasks D. Regulatory fees. 55. According to the \"Code for Valuation of Construction Projects\" (CB505000-2013), when preparing the bill of quantities, the labor costs listed in the daily rate table should be categorized according to (A). A. Job type B. Professional title C. Position D. Technical level