Let’s work on Question 40-2 from the 2015 First-Class Constructor Exam in \"Engineering Economics\": 60 multiple-choice questions – there are rewards for correct answers

2015-11-02View Original

Thread Content

Those who come to do exercises every day are the eager learners among our users! ! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some exam questions from this year’s first-level constructor examination have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give rewards to those who provide correct answers. ******************************************60. When the preliminary design of a construction project is not detailed enough to allow for an accurate calculation of the workload, but the technology used in the project is mature and similar benchmarks are available, what method should be employed to prepare an estimate for the design of such a project? A. Unit price expansion method B. Similar project substitution method C. Production capacity index method D. Estimation index method Answer: D 【Expert explanation】Since similar indicators are available, the estimation index method is the most suitable approach for preparing design estimates. See page P205 of the textbook.
Reply #22015-11-02
D. Estimation index method-------------------------------
Reply #32015-11-02
I choose the last option, D :D
Reply #42015-11-02
B. Similar project substitution method B. Similar project substitution method
Reply #52015-11-02
When the preliminary design depth of a construction project in a certain entity is insufficient to allow for an accurate calculation of the workload, but the technologies used in the project are relatively mature and there are similar benchmarks available, the appropriate method for preparing an estimate for the design of such a project is. D. Estimation index method
Reply #62015-11-02
D. The estimated index method should be the correct answer
Reply #72015-11-03
D. Estimation index method! ! ! ! !

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.