Everyone, take question 45-2: multiple-choice questions from the 2015 First-Class Constructor Examination in Project Management, questions 09-10; there will be a reward for those who answer correctly

2015-11-05View Original

Thread Content

Those who come to do exercises every day are the eager learners among our users! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some exam questions from this year’s first-level constructor examination have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give rewards for correct answers. ****************************************** 9. A certain construction project team formulates standards for material issuance based on the actual material consumption in previous projects, taking into account the specific requirements of the current construction project. This method of controlling the amount of material used is ( ). A. Quota control B. Measurement control C. Index control D. Lump-sum control. Answer: C. 10. Regarding the project management objectives and tasks of the contractor, which statement is correct? A. The contractor’s project management serves only the interests of the contractor itself. B. Contractor’s project management does not involve the preparation phase prior to commencement of work. C. The contractor’s cost targets are determined by the construction company based on its own production and operational conditions. D. The contractor is not responsible for the goals and tasks assigned by the owner to subcontractors. Answer: C
Reply #22015-11-05
9、C. Standard indicators are established based on past project experience, and materials are issued according to these indicators------------------------------10, C. --------------------------------------
Reply #32015-11-05
9.c.10.b................
Reply #42015-11-05
A construction project department formulates standards for material issuance to control supply, based on the actual material consumption in previous projects and taking into account the specific requirements of the current construction project. This method for controlling the amount of material used is (a) A fixed-quantity control
Reply #52015-11-05
10. Regarding the project management objectives and tasks of the constructor, the correct statement is (d).
Reply #62015-11-05
9 C refers to index control. 10 C. The cost target for the contractor is determined by the construction company itself, based on its production and operational conditions
Reply #72015-11-05
9. A certain construction project department formulates standards for material issuance and control, based on the actual material consumption in previous projects as well as the specific requirements of the current construction project. This method for controlling the amount of this material is (C)
Reply #82015-11-05
10. Regarding the project management objectives and tasks of the constructor, which statement is correct? ( C )
Reply #92015-11-06
9. A certain construction project department formulates standards for material issuance and control, based on the actual material consumption in previous projects as well as the specific requirements of the current construction project. This method for controlling the amount of this material is (C)
Reply #102015-11-06
10. Regarding the project management objectives and tasks of the constructor, the correct statement is (C).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.