Everyone, take question 57-2: multiple-choice questions 35-36 from the 2015 First-Class Constructor Examination in Project Management; there will be a reward for those who answer correctly

2015-11-11View Original

Thread Content

Let’s work on question 57-2015 from the First-Class Constructor Examination’s \"Project Management\" section: multiple-choice questions 35-36. There are rewards for those who answer them correctly. Those who do these exercises every day are truly enthusiastic learners! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some exam questions from this year’s first-level constructor examination have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give a reward for correct answers. ******************************************35. The quality control of preparatory work for construction techniques includes ( ) A. Defining quality control methods, B. Measurement control, C. Inspection control, D. Control of the construction layout plan. Correct answer: A. 36. In a bid submission under a unit-price contract, the bidder made obvious errors in the numerical calculations, resulting in discrepancies between the total price and the unit prices. Which of the following actions falls within the owner’s rights? A. The owner has the right to make corrections first before evaluating the bid, using the total price as the final figure. B. The owner does not have the right to make corrections first; they can simply disqualify that bidder. C. The owner does not have the right to make corrections first; they can ask the bidder to submit another bid. D. The owner has the right to make corrections first, using the adjusted total price based on the unit prices as the final figure. Correct answer: D
Reply #22015-11-11
Quality control of the preparatory work for construction techniques includes (a b c): A. Defining quality control methods, B. Measurement control, C. Inspection control
Reply #32015-11-11
36. In the bid document for a unit-price contract, the bidder made obvious errors in the numerical calculations, resulting in discrepancies between the total price and the price per unit. Among the following actions, which one is an entitlement of the owner? (d) The owner has the right to make corrections first and then proceed with the evaluation, using the total price adjusted based on the unit price as the final bid amount
Reply #42015-11-11
35 A. Define quality control methods 36 D The owner has the right to make modifications first and then conduct an evaluation; the total price adjusted based on the unit price shall serve as the final quote
Reply #52015-11-11
35. The quality control of preparatory work for construction techniques includes (A) A. Defining quality control methods, B. Measurement control, C. Inspection control, D. Control of the construction layout plan. 36. In a bid submission under a unit-price contract, the bidder made obvious errors in the numerical calculations, resulting in discrepancies between the total price and the unit prices. Among the following options, which one represents the rights of the owner? (D) A. The owner has the right to make corrections first before evaluating the bid, using the total price as the final figure. B. The owner does not have the right to make corrections first; they can simply disqualify that bidder. C. The owner does not have the right to make corrections first; they can ask the bidder to submit another bid. D. The owner has the right to make corrections first, using the adjusted total price based on the unit prices as the final figure
Reply #62015-11-12
A. Define the quality control methods. D. The owner has the right to make modifications first and then conduct an evaluation; the total price adjusted based on the unit price shall serve as the final quote
Reply #72015-11-16
35. The quality control of preparatory work for construction techniques includes (A) A. Defining quality control methods, B. Measurement control, C. Inspection control, D. Control of the construction layout plan. 36. In a bid submission under a unit-price contract, the bidder made obvious errors in the numerical calculations, resulting in discrepancies between the total price and the unit prices. Among the following options, which one represents the owner’s rights? (B) A. The owner has the right to make corrections first before evaluating the bid, using the total price as the final figure. B. The owner does not have the right to make corrections first; they can declare that bid invalid. C. The owner does not have the right to make corrections first; they can ask the bidder to submit another bid. D. The owner has the right to make corrections first, using the adjusted total price based on the unit prices as the final figure

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.