Regarding pump purging

2016-11-07View Original

Thread Content

During system purging, is it done by removing the filter at the pump inlet and the check valve at the outlet for purging, but what about the parts of the pump that are not subjected to purging? How should those be dealt with?
Reply #22016-11-08
This post was last edited by ylb913 on 2016-11-8 06:24. The pump body needs to be replaced when it stops operating; no purging is required when it starts up for the first time.
Reply #32016-11-08
The system purging does not pass through the pump; there is a connection line in front of the pump’s inlet valve and behind its outlet valve – that is a dedicated purging line. The pump section needs to be handled separately. High-temperature pumps can be purged solely with steam. Steam is not allowed to enter pumps that are not at high temperatures. Design agencies typically provide corresponding purging or replacement methods, such as nitrogen purging or water washing; if no such measures are in place, replacement is generally not necessary.
Reply #42016-11-08
Remove the pump inlet and outlet flanges, as well as the filters and check valves, and install blind flanges at the pump’s inlet and outlet to prevent debris from being blown into the pump. In particular, it is important to prevent debris from reaching the seals, as this could damage them once the pump starts operating
Reply #52016-11-09
Pumps generally do not require purging; proper isolation should be ensured during construction, and under normal circumstances the conditions inside the pump can be maintained
Reply #62016-11-09
System purging generally involves treating the pipelines; for steam purging, it is necessary to isolate equipment such as pumps, by using things like blind flanges. Equipment such as pumps does not require any special treatment; it is relatively clean when it leaves the factory. As for the short pipes at the inlet and outlet, filters can be installed during the first water testing of the equipment. In any case, all filters need to be cleaned or replaced during the first feeding process.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.