Thread Content
This post was last edited by Desert Fish on 2015-11-14 08:02. Everyone, please work on Question 61-2: the multiple-choice questions 43–43 from the 2015 First-Class Constructor Examination in Project Management. There will be rewards for those who answer correctly. Those who do these exercises every day are truly eager learners! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some exam questions from this year’s First-Class Constructor exam have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive a reward from the moderator. ****************************************** After completing the questions, it’s time to rest. Everyone is encouraged to click on the posts in the food category: there are summary posts on various food-related searches, and everyone is welcome to share their own content. 43. Which of the following methods for inspecting and approving construction work is correct? A. Inspection lots with general defects should be redone. B. When certain criteria are not met, acceptance is still possible. C. If serious defects can meet the requirements for safe use after reinforcement, acceptance can be carried out in accordance with the technical treatment plan. D. For sub-projects that still do not meet the requirements for safe use even after reinforcement, acceptance can be done with some items omitted. 【Standard answer】C 44 The five elements of the communication process include ( ) A. Communicator, communicated to, communication medium, communication environment, and communication channel B. Communicator, communicated to, communication medium, communication content, and communication channel C. Communicator, communicated to, communication medium, communication environment, and communication method D. Communicator, communicated to, communication medium, communication content, and communication method Standard answer: A
43 C. Severe defects can meet the requirements for safe use after reinforcement, and acceptance can be carried out in accordance with the technical treatment plan. 44 A: Communicating entity, communicated entity, communication medium, communication environment, and communication channels
43. Among the following practices for the acceptance of construction inspection lots, the correct one is (C). A. Inspection lots with general defects should be redone. B. When certain criteria are not met, acceptance is still possible. C. If serious defects can meet the requirements for safe use after reinforcement, acceptance can be carried out in accordance with the technical treatment plan. D. For sub-projects that still do not meet the requirements for safe use even after reinforcement, acceptance can be conducted with some items omitted. 44 The five elements of the communication process include (A) A. Communicators, communicated to, communication medium, communication environment, and communication channels B. Communicators, communicated to, communication medium, communication content, and communication channels C. Communicators, communicated to, communication medium, communication environment, and communication methods D. Communicators, communicated to, communication medium, communication content, and communication methods
Among the following practices for the acceptance of construction inspection lots, the correct one is (c). C. Severe defects can meet the requirements for safe use after reinforcement, and acceptance can be carried out in accordance with the technical treatment plan
The five elements of the communication process include (a) the communicator, the message recipient, the communication medium, the communication environment, and the communication channels
43. Among the following practices for the acceptance of construction inspection lots, the correct one is (C). A. Inspection lots with general defects should be redone. B. When certain criteria are not met, acceptance is still possible. C. If serious defects can be rectified so that the structure meets safety requirements, acceptance can be carried out in accordance with the technical treatment plan. D. For sub-projects that still do not meet safety requirements after reinforcement, acceptance can be done with some items omitted. 44 The five elements of the communication process include (A) A. Communicators, communicated to, communication medium, communication environment, and communication channels B. Communicators, communicated to, communication medium, communication content, and communication channels C. Communicators, communicated to, communication medium, communication environment, and communication methods D. Communicators, communicated to, communication medium, communication content, and communication methods