Treatment of saturated waste brine (sodium sulfate to sodium chloride ratio 1; around 1)

2015-11-24View Original

Thread Content

Our factory generates wastewater containing saturated sodium sulfate and sodium chloride during the production process; how should this wastewater be treated?
Reply #22015-11-25
The salts are extracted in stages, based on the differences in their solubility with temperature.
Reply #32015-11-26
Evaporation crystallization: The approach I just proposed is the same as yours. Initial treatment is required, followed by evaporation crystallization; salt can be treated either together or separately
Reply #42015-12-21
The MVR technology can be used; it’s best to determine the relevant boiling point parameters of the original liquid before proceeding with the design. I have operated this technology in the field
Reply #52016-01-21
Let me explain the specific water quality details. We specialize in wastewater treatment, and we’ll also bring up your requirements
Reply #62016-01-21
If no organic matter is present in the preliminary treatment, fractional crystallization can be carried out to recover sodium sulfate and sodium chloride separately
Reply #72016-01-23
It’s all saturated; only evaporation and crystallization are possible now
Reply #82016-01-27
This post was last edited by zhaolijun on 2016-1-30 at 17:08. It mainly involves evaporation crystallization; preliminary pretreatment may also be required. Please contact if needed
Reply #92016-01-29
In industrial wastewater treatment projects, organic wastewater containing sodium sulfate and sodium chloride generally has a high salt content as well as a high COD level. For such wastewater with high salt levels and high COD, oxidation or evaporation processes can be employed; however, an accurate treatment plan can only be devised after assessing the quality and volume of the wastewater. Our company specializes in the production of MVR evaporators; to treat each cubic meter of wastewater, only approximately 35 to 70 kilowatt-hours of electricity are required. If you are interested in learning more, you can send me a private message.
Reply #102016-03-08
For sodium sulfate and sodium chloride, the MVR system for these materials is relatively simple; I have calibrated no fewer than 10 sets of MVR systems for such materials on-site.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.