【Daily Question】Question from the 20151126 issue

2015-11-26View Original

Thread Content

This post was last edited by yuchenchf on 2015-11-30 at 16:18. Reward for participation: 2 Wealth. Reward for correct answer: 9 wealth. Progress tracking and control reports are the results of comparing quantitative data based on progress ( ). A. Predicted value vs. planned value B. Planned value vs. actual value C. Actual value vs. predicted value D. Planned value vs. standard quota value 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-26
B. Planned values and actual values: Project progress tracking and control reports are the result of comparing quantitative data based on the project’s (B) values.
Reply #32015-11-26
Progress tracking and control reports are the result of comparing quantitative data based on progress (B: planned values versus actual values).
Reply #42015-11-26
Progress tracking and control reports are the results of comparing quantitative data based on progress (B). A. Predicted value and planned value B. Planned value and actual value C. Actual value and predicted value D. Planned value and standard quota value
Reply #52015-11-26
There is a typo: The actual value. Progress tracking and control reports are the results of comparing quantitative data based on the progress ( ). A. Predicted value and planned value B. Planned value and actual value C. Actual value and predicted value D. Planned value and standard value 【Correct answer】B 【Answer explanation】This question examines the application of dynamic control methods in construction management. The comparison between the planned and actual values of progress should be a quantitative data comparison, and the result of this comparison is the progress tracking and control report. See page P30 of the textbook.
Reply #62015-11-26
B: Planned value and actual value. (The alternative answer contains spelling errors)
Reply #72015-11-26
Progress tracking and control reports are the results of comparing quantitative data based on progress (B). A. Predicted value and planned value B. Planned value and a dozen or so values C. Actual value and predicted value D. Planned value and standard quota value
Reply #82015-11-26
B. Planned value vs. actual value – (There’s a typo in the question)
Reply #92015-11-26
Progress tracking and control reports are the results of comparing quantitative data based on progress (B). A. Predicted value and planned value B. Planned value and a dozen or so values C. Actual value and predicted value D. Planned value and standard quota value
Reply #102015-11-26
Progress tracking and control reports are the results of comparing quantitative data based on progress (B). A. Predicted value and planned value B. Planned value and a dozen or so values C. Actual value and predicted value D. Planned value and standard quota value

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.