Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Multiple-choice question: Regarding the removal of formwork for post-tensioned prestressed concrete beams, which of the following statements are correct? ( ) A. The side formwork of the beam should be removed before prestress tensioning. B. The side formwork of the beam should be removed after prestress tensioning. C. The side formwork can be removed once the concrete strength meets the requirements for its removal. D. The bottom formwork of the beam should be removed after prestress tensioning. E. The bottom formwork of the beam should be removed before prestress tensioning
A, C, E,--------------------------
Regarding the removal of formwork for post-tensioned prestressed concrete beams, the correct options are (A C E). A. The side formwork of the beam should be removed before prestress tensioning. B. The side formwork of the beam should be removed after prestress tensioning. C. The side formwork can be removed once the concrete strength meets the requirements for its removal. D. The bottom formwork of the beam should be removed after prestress tensioning. E. The bottom formwork of the beam should be removed before prestress tensioning
Regarding the removal of formwork for post-tensioned prestressed concrete beams, the correct options are (A C E). A. The side formwork of the beam should be removed before prestress tensioning. B. The side formwork of the beam should be removed after prestress tensioning. C. The side formwork can be removed once the concrete strength meets the requirements for its removal. D. The bottom formwork of the beam should be removed after prestress tensioning. E. The bottom formwork of the beam should be removed before prestress tensioning