Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Regarding cost-plus contract agreements, which statement is correct? () A. Using this pricing method is not conducive to the owner’s investment control. B. Cost-plus contracts are not suitable for emergency rescue and disaster relief projects. C. Cost-plus contracts are not appropriate for project management contracts. D. For contractors, cost-plus contracts carry higher risks than fixed-price contracts. [Haichuan Thanksgiving] – Production Division. The Production and Management Division is seeking moderators and technical discussants to join us
Reply #22016-02-15
A. Using this pricing method is unfavorable for the owner’s investment control
Reply #32016-02-15
A. Using this pricing method is unfavorable for the owner’s investment control
Reply #42016-02-15
Regarding cost-plus contract agreements, the correct statement is (A). A. Using this pricing method is unfavorable for the owner’s investment control. B. Cost-plus contracts are not suitable for emergency rescue and disaster relief projects. C. Cost-plus contracts are not appropriate for project management contracts. D. For contractors, cost-plus contracts carry higher risks than fixed-price contracts
Reply #52016-02-15
Regarding cost-plus contract agreements, the correct statement is (A). A. Using this pricing method is unfavorable for the owner’s investment control. B. Cost-plus contracts are not suitable for emergency rescue and disaster relief projects. C. Cost-plus contracts are not appropriate for project management contracts. D. For contractors, cost-plus contracts carry higher risks than fixed-price contracts
Reply #62016-02-15
Regarding cost-plus contract agreements, the correct statement is (A). A. Using this pricing method is unfavorable for the owner’s investment control. B. Cost-plus contracts are not suitable for emergency rescue and disaster relief projects. C. Cost-plus contracts are not appropriate for project management contracts. D. For contractors, cost-plus contracts carry higher risks than fixed-price contracts
Reply #72016-02-15
Regarding cost-plus contract agreements, the correct statement is (A). A. Using this pricing method is unfavorable for the owner’s investment control. B. Cost-plus contracts are not suitable for emergency rescue and disaster relief projects. C. Cost-plus contracts are not appropriate for project management contracts. D. For contractors, cost-plus contracts carry higher risks than fixed-price contracts
Reply #82016-02-15
A. Using this pricing method is unfavorable for the owner’s investment control

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.