Can liquid ammonia unloading and liquid ammonia cylinder filling be carried out in the same location?

2016-02-21View Original

Thread Content

Can liquid ammonia unloading and liquid ammonia cylinder filling be carried out in the same location?
Reply #22016-02-21
It is recommended not to place them together, as cross-operation poses a risk of liquid ammonia leakage. Following our standard management approach, whenever there is cross-tasking that involves risks, it must be strictly controlled to prevent its occurrence.
Reply #32016-02-22
Okay, thank you! Also, is the distance between the filling station and the overhead cable calculated as 1.5 times the pole height?
Reply #42016-02-22
It is generally designed at 1.5 times the rate~
Reply #52016-02-23
Are you referring to the tank area for unloading and the cylinder filling site? The liquid ammonia cylinder filling station is classified as a Category B factory building, and it must maintain a fire separation distance from the tank area.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.