【Chemical Operations】Regarding the startup plan for the liquefied gas tank farm

2016-03-03View Original

Thread Content

This post was last edited by Xiao Gong 1985 on 2016-3-3 at 17:10. After the piping work in the LPG tank area is completed but before handover, pressure testing and airtightness checks of the pipelines will be carried out. It seems that there is a lack of organization in this process, and I hope to draw on the experience of those who are more experienced than me. We are now seeking a relevant startup preparation plan, including pipeline pressure testing, water flushing, gas tightness testing of spherical tanks, individual unit testing, water circulation testing, nitrogen purging, etc.! Email address: lf871010@163.com
Reply #22016-03-13
After the flaw detection is completed, a hydrostatic test and a settlement test are carried out first, followed by nitrogen purging and a gas-tightness test based on the actual conditions.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.